CREE Wolfspeed Mohawk Valley NanoCenter

CREE Wolfspeed Mohawk Valley NanoCenter Project Description SCOPE: 450 Acre site, 458,000 sf, four-story Fabrication Facility; 85,000 sf four-story Administration Building; 50,000 cy of concrete foundations and elevated slabs Current Status: Foundations are complete and work continues on slabs on deck with our in-house ACI Certified Flatwork Crews. See the full story here: https://www.jersen.com/one-year-later-crees-1b-factory-in-upstate-new-york-is-on-schedule-even-in-a-pandemic/ ARCHITECT: Excyte U.S., Inc. […]

CREE Wolfspeed Mohawk Valley NanoCenter Read More »

GlobalFoundries, Admin Building, FAB8

GlobalFoundries, Admin Building, FAB8 Project Description PROJECT TYPE: Chip Fabrication & Office SCOPE: 200,000 Square Feet, 4 Stories, LEED Certified: Gold, Concrete Superstucture, 1.1 Million Square Feet, Class 100 Clean Rooms ARCHITECT: M+W Group VALUE: $60,000,000 INDUSTRY: Commercial, Technology Project Details DATE: Varied DURATION: 14 Months Related Projects

GlobalFoundries, Admin Building, FAB8 Read More »

SUNY Albany ETEC Early Site Package

SUNY Albany ETEC Early Site Package Project Description SCOPE: The SUNY Albany Emerging Technology and Entrepreneurship Complex (ETEC) Early Site project is located on the Harriman State Office Campus neighboring the SUNY Albany Campus. The early site package consisted of clearing a 12 acre site, massive site cuts/fills, contaminated soil management, installation of new storm

SUNY Albany ETEC Early Site Package Read More »

State of New York at Albany – Data Center (Tier III)

State of New York at Albany – Data Center (Tier III) Project Description PROJECT TYPE: SUNY Data Center SCOPE: Demolitions, additions, Precast exterior walls, structural steel, utilities, sitework, concrete, masonry & computer flooring ARCHITECT: Woodward Connors Gillies Seleman VALUE: $24,000,000 INDUSTRY: Commercial, Technology Project Details DATE: 2012 DURATION: 20 Months Related Projects Related Projects

State of New York at Albany – Data Center (Tier III) Read More »

Fillpoint/SVG

Fillpoint/SVG Project Description PROJECT TYPE: Office/Warehouse SCOPE: 37,000 Square Feet, New Construction, LEED Certified ARCHITECT:  Jersen In-house Design/Build VALUE: $2,800,000 INDUSTRY: Commercial, Technology Project Details DATE: 2007 DURATION: 3 Months Related Projects

Fillpoint/SVG Read More »

RPI EMPAC

RPI EMPAC Project Description PROJECT TYPE: Auditorium/Performing Arts Center SCOPE: Massive Concrete Foundations and Superstructure, Site Concrete, LEED Certified ARCHITECT: Davis Brody Bond, LLP. VALUE: $18,500,000 INDUSTRY: Education, Technology Project Details DATE: 2004 DURATION: 10 Months Related Projects

RPI EMPAC Read More »

Nano Fab Xtention Project College of Nanoscale Science and Engineering, SUNY- Albany, NY

Nano Fab Xtention Project College of Nanoscale Science and Engineering, SUNY- Albany, NY Project Description PROJECT TYPE: New Nano Technology Complex known as NFX SCOPE: Performed concrete work at waffle slab and topping slabs throughout new complex. ARCHITECT: CH2M, EYP, CME VALUE: $8,400,000 INDUSTRY: Technology Project Details DATE: 2011 DURATION: 4 Months Related Projects

Nano Fab Xtention Project College of Nanoscale Science and Engineering, SUNY- Albany, NY Read More »

Schenectady Bureau of Services

Schenectady Bureau of Services Project Description PROJECT TYPE: Municipal Public Works Dept SCOPE: 8 New Buildings including Main Offices, Vehicle Storage and Maintenance, Salt Shed, Fueling Stations, and Wash Bay, LEED Certified ARCHITECT: Peterson Group Architects VALUE: $18,700,000 INDUSTRY: Industrial, Technology Project Details DATE: 2009 DURATION: 18 Months Related Projects

Schenectady Bureau of Services Read More »