6 Industry Drive
Waterford, NY 12188

CREE Wolfspeed Mohawk Valley NanoCenter

Project Description

SCOPE:

450 Acre site, 458,000 sf, four-story Fabrication Facility;
85,000 sf four-story Administration Building; 
50,000 cy of concrete foundations and elevated slabs

Current Status: Foundations are complete and work continues on slabs on deck with our in-house ACI Certified Flatwork Crews.

See the full story here: https://www.jersen.com/one-year-later-crees-1b-factory-in-upstate-new-york-is-on-schedule-even-in-a-pandemic/

ARCHITECT:

Excyte U.S., Inc.

VALUE:

$30M

INDUSTRY:

Commercial / Technology

Project Details

DATE:

April – December 2020

DURATION:

9 months