North Ferry Street Pump Station Improvements
Project Description
SCOPE:
106′ diameter support of excavation system, active deep well dewatering and bulk excavation for a four-story concrete pump station. Underground water, sanitary force and gravity piping. Interior process piping systems inclusive of building automation, pumps, valves and appurtenances and material handling inc. bridge cranes, vertical reciprocating conveyors and monorails.
Current Status: We have achieved bottom of excavation depth of 30′ from existing grade. Our excavation support system lies within 70′ of the banks of the Mohawk River and our micro pile crews are progressing with the 183 deep foundation piles required.
ARCHITECT:
CHA Consulting, Inc.
VALUE:
$18.1 M
INDUSTRY:
Municpal Water / Sewer Treatment
Project Details
DATE:
April 2020 – June 2021
DURATION:
15 months